Andy, Gyt, Ryan and Keith went down to Crowley's to begin our summer preparations today. We prepared for a number of projects and also greased all the winches.
Next Saturday we hope to continue working and are scheduled to meet at 10am.
We have decided to utilize our spare B&G display near the nav-station and Gyt will have this ready for install next week. We still need to order the forward stanchion as the current spare we have is not correct. Andy measured for the new halyards and will place orders this week. The water tank has been removed and preparations have been made for installing the required lead bars to make the hull weigh in.
Items for next week:
- Grab Rails reinstall
- fantastick interior
- install instruments and electronics
- dodger mounts need to be re caulked
- chain plate re caulking.
- install wheel
- install batteries